Construction Progress Of Gateway Thao Dien
Tuesday, 20 June, 2017
By the first week of June 2017, progress is as follows:
Block A (ASPEN):
-
Structure work: 42F slab: completed, Roof floor slab: on going.
-
Finishing work: under construction: brick work, plastering work, aluminium door/ window frame, wooden door frame, waterproofing, tile work,…: from 5F to 35F.
Block B (MADISON):
-
Structure work: Roof floor slab: completed, Upper roof floor: on going.
-
Finishing work: under construction: brick work, plastering work, aluminium door/ window frame, wooden door frame, waterproofing, tile work,…: from 5F to 32F.
Block C (BERKLEY):
-
Structure work: 5F slab: on going.
Block D (ALBANY):
-
Structure work: 7F slab: on going.