Construction Progress Of Gateway Thao Dien

Tuesday, 20 June, 2017

By the first week of June 2017, progress is as follows:

Block A (ASPEN): 

  • Structure work: 42F slab: completed, Roof floor slab: on going.

  • Finishing work: under construction: brick work, plastering work, aluminium door/ window frame, wooden door frame, waterproofing, tile work,…: from 5F to 35F.

Block B (MADISON):

  • Structure work: Roof floor slab: completed, Upper roof floor: on going.

  • Finishing work: under construction: brick work, plastering work, aluminium door/ window frame, wooden door frame, waterproofing, tile work,…: from 5F to 32F.

Block C (BERKLEY):

  • Structure work: 5F slab: on going.

Block D (ALBANY):

  • Structure work: 7F slab: on going.